University of Malta – Msida

 

Description of the works

Construction of Underground Materials Engineering Labs at University of Malta

 

Duration of the Works: 1 year

Client: University of Malta

Architect: Team 2 Architects

 

Construction Methodology

  • Excavation
  • Earthing System
  • Construction of R/C Footings and Foundations
  • Construction of RC Ground slabs
  • Waterproofing
  • Vibration Insulation
  • Construction of R/C Walls
  • Installation of services for reservoir
  • Construction of Waffle Slab
  • Construction of Steel Structure at Ground Floor Level

Comments are closed.